Short answer
A wall of modular brick with 3/8 in joints takes 675 bricks and 5.5 cu ft of mortar per 100 sq ft, which is 6.75 bricks per sq ft or 72.7 per m² (Brick Industry Association). German NF bricks with 10 mm head and 12 mm bed joints come to about 48 per m². Add at least 5 % to the bricks and 15 to 25 % to the mortar.
Calculate it
Brick and block calculator
Bricks or blocks per wall and the mortar to lay them.
Brick and block calculator →Bricks per square foot and per square metre
The Brick Industry Association (BIA) Technical Note 10 lists the quantity of brick and mortar per 100 sq ft of wall for each standard size, without waste. The figures below are for a single wythe laid in the usual running bond with 3/8 in (9.5 mm) joints. The per m² column divides the same count by 9.29 m², the area of 100 sq ft.
| Brick (nominal size) | Bricks per 100 sq ft | Bricks per m² | Mortar per 100 sq ft | Mortar per m² |
|---|---|---|---|---|
| Modular (4 × 2⅔ × 8 in) | 675 | 72.7 | 5.5 ft³ | 16.8 l |
| Engineer Modular (4 × 3⅕ × 8 in) | 563 | 60.6 | 4.8 ft³ | 14.6 l |
| Roman (4 × 2 × 12 in) | 600 | 64.6 | 6.4 ft³ | 19.5 l |
| Norman (4 × 2⅔ × 12 in) | 450 | 48.4 | 5.1 ft³ | 15.5 l |
| Utility (4 × 4 × 12 in) | 300 | 32.3 | 3.7 ft³ | 11.3 l |
Modular is the common US brick. BIA gives its specified size as 3⅝ × 2¼ × 7⅝ in (92 × 57 × 194 mm). Divide the 100 sq ft figures by 100 for a count per square foot: modular is 6.75, Roman 6.0, Norman 4.5.
NF and DF bricks with German joints
German bricks follow the octametric system. Baunetz Wissen and Baukobox list the normal format NF as 240 × 115 × 71 mm and the thin format DF as 240 × 115 × 52 mm. Baukobox states the rule: one length equals two widths plus one joint, so the head joint is 240 − 2 × 115 = 10 mm. Baunetz gives the bed joint as usually 12 mm with normal mortar, and 1 to 3 mm with thin-bed mortar. The course height is the brick height plus the bed joint.
For NF with a 12 mm bed joint the course is 71 + 12 = 83 mm, so 1 m of wall height holds 12.05 courses. Each course has 1 / 0.25 = 4 bricks per metre, since a brick plus a head joint occupies 250 mm. That is 12.05 × 4 = 48.2 bricks per m² for a 115 mm wall. For DF the course is 52 + 12 = 64 mm, which gives 62.5 bricks per m².
These are counts from the dimensions, for solid rectangular units. Brick sold with perforations or a frog uses the same count but a different volume of mortar, so check the manufacturer's data sheet if you need the mortar to the litre.
How much mortar
BIA gives 5.5 cu ft of mortar per 100 sq ft of modular brick with 3/8 in joints, and 6.9 cu ft with 1/2 in joints. In metric that is 16.8 and 21.0 litres per m². The thicker joint adds about a quarter more mortar for the same area of wall.
For NF with a 12 mm bed joint and 10 mm head joint, the mortar is what remains of the wall volume once the bricks are taken out: 0.115 m³ per m² of wall minus 48.2 × 0.24 × 0.115 × 0.071 m³ leaves 0.0206 m³, or about 20.6 litres per m². DF comes to 25.3 litres per m², because there are more joints.
BIA also gives a rule of thumb for bagged mortar: eight bags of masonry cement lay about 1,000 modular brick, including an unspecified amount of waste.
Worked example: a 10 × 8 ft wall in modular brick
Area: 10 × 8 = 80 sq ft, with no openings.
- Bricks: 80 × 6.75 = 540. With BIA's minimum 5 % waste, 567.
- Mortar: 80 × 0.055 = 4.4 cu ft. With 15 to 25 % waste, 5.1 to 5.5 cu ft, or 5.3 cu ft at 20 %.
Subtract doors and windows from the wall area first. BIA says higher percentages than 5 % may be needed depending on job conditions.
Worked example: a 5 × 2.5 m wall in NF brick, in metric
Area: 5 × 2.5 = 12.5 m². Wall 115 mm thick, bed joint 12 mm, head joint 10 mm.
- Bricks: 12.5 × 48.2 = 602.4, so 603 net. With 5 % waste, 632.5, so 633.
- Mortar: 12.5 × 20.6 litres = 257 litres, about 0.26 m³. With 20 % waste, 308 litres; the 15 to 25 % range is 296 to 321 litres.
Round the brick count up once, after the waste is added.
Waste allowance
BIA recommends adding at least 5 % to the net brick quantity delivered to the site, and 15 to 25 % to the net mortar quantity. Mortar takes the larger allowance. The calculator defaults to 5 % for bricks and 20 % for mortar, the middle of BIA's range.
Questions
How many bricks are in a square foot of wall?
6.75 modular bricks with 3/8 in joints, from BIA's figure of 675 per 100 sq ft. Roman is 6.0 and Norman 4.5. The count does not include waste.
How many bricks per m² of wall?
About 72.7 modular bricks, or about 48 German NF bricks (240 × 115 × 71 mm) with a 12 mm bed joint and 10 mm head joint, for a one-brick-thick wall of 115 mm.
How much mortar do I need per square metre of brick wall?
About 16.8 litres for modular brick with 3/8 in joints (BIA), and about 20.6 litres for NF brick with a 12 mm bed joint, before adding 15 to 25 % for waste.
How much extra brick should I order?
At least 5 % over the net quantity, according to BIA. More if the wall has many corners, openings or cut bricks.
What is the difference between NF and DF brick?
Both are 240 mm long and 115 mm wide. NF is 71 mm high and DF is 52 mm high, so DF gives about 62.5 bricks per m² of wall against 48.2 for NF.
Does a thinner joint reduce the number of bricks?
No, it increases it slightly, because each course gets shorter. It reduces the mortar. BIA gives 5.5 cu ft per 100 sq ft with 3/8 in joints against 6.9 with 1/2 in joints.
Calculate it
Brick and block calculator
Bricks or blocks per wall and the mortar to lay them.
Brick and block calculator →Sources
- [1]Technical Notes on Brick Construction 10: Dimensioning and Estimating Brick Masonry (February 2009). Brick Industry Association. Modular brick 3⅝ × 2¼ × 7⅝ in with ⅜ in joints: 675 brick and 5.5 cu ft mortar per 100 sq ft, without waste. Add at least 5 % to brick and 15–25 % to mortar.. Checked November 5, 2026
- [2]Glossar: NF Normalformat; Lagerfuge. Baunetz Wissen. NF brick 240 × 115 × 71 mm; bed joint with normal mortar usually 12 mm, thin-bed mortar 1–3 mm; course height = brick height + bed joint.. Checked November 5, 2026
- [3]Masonry formats. Baukobox. NF 240 × 115 × 71 mm, DF 240 × 115 × 52 mm; octametric rule length = 2 × width + one joint, so the head joint is 240 − 2 × 115 = 10 mm.. Checked November 5, 2026